BUILDING PROJECT 2024

BACKGROUND

Expansion of the current facility is necessary due to the growth of the current transit operation. More space and storage is needed to allow for more efficient operations management. The expansion of the current building to allow for transit growth. The planned expansion will include transit offices, rest rooms, transit maintenance parts storage, additional parking bays for transit buses, van, and transit support vehicle parking. Lights, blacktop, and additional client/employee parking area are included. -SEP2020

RESOLUTION

NOW, THEREFORE, BE IT RESOLVED THAT Semcac's Board of Directors agrees to enter into a contract with MnDOT for purchase of land, design, and construction of an addition to the current facility. Further resolved that Semcac agrees to provide 20 percent of the total capital costs outlined in the MnDOT Grant contract. -SEP2022

1



SPRING 2024 MNDOT MEETINGS CONTRACT
2



AUG2024 DESIGN
3



JAN2025 BIDS
4



MAY2025 CONSTRUCTION BEGINS